The following construction projects are anticipated to affect highways in Vinton County next week. All outlined work is weather permitting. Click on each project to see its location at OHGO.com.

SR 160 landslide - One lane of SR 160 is closed between Township Road 5 and SR 349 due to a landslide. Temporary traffic signals and a 10 foot width restriction are in place. Estimated completion: Sept. 1, 2020.

SR 327 landslide - One lane of SR 327 is closed between West Junction Road (County Road 46) and US 50 due to a landslide. Temporary traffic signals and a 10 foot width restriction are in place. Estimated completion: Sept. 30, 2020.

SR 124 culvert replacement - SR 124 is closed between Hawk Station Road (County Road 9) and SR 160 for a culvert replacement project. ODOT's detour is SR 160 to SR 32 to SR 124. Estimated completion: Aug. 14, 2020.